KNOWBASE
KB-2402Wrongdoing Confirmed

Mumbai Metro-3's Car Shed U-Turn

A metro depot planned for Aarey Colony was scrapped for a forest-free site, then reinstated by a later government — with tree-felling, court stays, and two changes of site adding years of delay and thousands of crores to the bill.

Public SpendingPublished 8 September 2026Updated 8 September 2026
₹4,000+ cr
estimated additional cost from shifting Mumbai Metro Line 3's car shed from Aarey Colony to Kanjurmarg in 2020, before a later government reversed the decision back to Aarey
Share on XShare on WhatsApp
01

The Promise

The car shed at Aarey will be built without harming the forest cover, and the metro will be operational on schedule.

Mumbai Metro Rail Corporation Limited (MMRCL) and the Maharashtra government, State-run implementing agency and state government for Mumbai Metro Line 3 · 1 January 2015

This reflects the general assurance MMRCL and the state government gave when the Aarey site was first selected for the car shed, rather than a verified quotation from a specific document, which this entry has not reviewed directly.

02

The Standard

That Mumbai Metro Line 3 (Colaba–Bandra–SEEPZ) would be built and commissioned on its original schedule and budget, with the car shed depot sited and constructed without becoming a prolonged point of litigation, political reversal, or major cost escalation.

MMRCL's original project cost and timeline estimates for Line 3, and Maharashtra's Tree Authority approval process for any felling required for the depot.

In force from 1 January 2015

03

The Reality

Work on the Aarey Colony car shed began in 2015, but activists and residents opposed it as damaging one of Mumbai's last significant green spaces. In October 2019, after the BMC's Tree Authority approved felling around 2,700 trees, MMRCL cut roughly 2,141 trees over a single night before the Supreme Court, on 7 October 2019, ordered a halt to further felling and set a hearing for 21 October. The incoming Shiv Sena–led government under Uddhav Thackeray then scrapped the Aarey site entirely in October 2020, shifting the car shed to Kanjurmarg — a decision MMRCL and government estimates put at adding roughly ₹4,000 crore or more to project costs and years of delay, on top of the roughly ₹100 crore already spent constructing at Aarey. After the Shinde-Fadnavis government took power in 2022, it reversed the decision again, directing the car shed back to Aarey, citing the Kanjurmarg site's own legal disputes over land ownership and the cost of further delay. Metro Line 3 has since opened in phases, with the Aarey car shed reported nearing completion years behind the project's original schedule.

As of 1 January 2024

04

The Gap

05

Money

Allocated
Not disclosed
Released
Not disclosed
~₹100 crore already spent constructing at Aarey before the 2020 shift order, reported as a sunk cost at the time
₹ 100 crore

Figures are estimates reported in contemporaneous press coverage rather than an audited reconciliation of total project cost overrun across all site changes; this entry has not reviewed MMRCL's or the state government's own cost accounting.

06

Timeline

  1. Announcement
    Aarey Colony selected as car shed site

    Construction begins on the Metro Line 3 depot in Aarey Colony amid opposition from environmentalists.

  2. Milestone
    BMC Tree Authority approves felling; trees cut overnight

    Around 2,141 trees are felled in Aarey before further action is halted, prompting large protests and detentions.

  3. Delay
    Supreme Court orders halt to further tree-felling

    Court registers a suo motu case and restrains authorities from cutting more trees pending a hearing later that month.

  4. Revision
    Thackeray government shifts car shed to Kanjurmarg

    State government scraps the Aarey site, citing the ecological concerns; MMRCL/government estimates put the added cost at roughly ₹4,000 crore.

  5. Revision
    Shinde-Fadnavis government reverses the decision back to Aarey

    New government cites land-title disputes over the Kanjurmarg site and further delay costs in ordering the car shed built at Aarey after all.

  6. Status
    Aarey car shed reported nearing completion

    Construction reported over 95% complete years behind the project's original schedule.

07

Legal Status

No criminal or corruption prosecution is reported in connection with the car shed site reversals; this is a case of policy flip-flopping and litigation (the Supreme Court's suo motu tree-felling case, and separate disputes over Kanjurmarg land title) rather than an alleged financial crime. The Supreme Court's suo motu proceeding on Aarey tree-felling and related environmental litigation has continued in phases alongside the project.

08

Verdict

Wrongdoing ConfirmedMedium confidence

This is a real, well-documented case of a major infrastructure project's site decision being reversed twice by successive state governments for a mix of environmental, legal, and political reasons, adding a widely reported multi-thousand-crore cost estimate and years of delay. It is a governance and planning failure rather than a proven case of financial crime, and this entry does not have a single authoritative reconciliation of the total added cost across both reversals.

The sequence of events — tree felling, the Supreme Court stay, the 2020 shift to Kanjurmarg, and the 2022 reversal back to Aarey — is corroborated across multiple independent outlets, and the ₹4,000 crore estimate is attributed to government/MMRCL sources at the time. This entry has not reviewed MMRCL's own cost filings or a CAG audit of the project, if one exists, and so cannot state a fully audited final cost overrun figure.

09

What remains incomplete

  • This entry has not found or reviewed an official CAG or MMRCL audit quantifying the total cost overrun across both site reversals (Aarey to Kanjurmarg to Aarey); the ₹4,000 crore figure covers only the 2020 shift estimate.
  • The current operational status and exact commissioning date of the Aarey car shed as of the most recent update is not confirmed beyond '95%+ complete' reporting from 2024.
  • Outcomes of the Kanjurmarg land-title dispute referenced as a reason for the 2022 reversal have not been independently verified by this entry.
10

Sources

Independent source1 July 2022
Devendra Fadnavis orders shifting Metro 3 car shed back to Mumbai's Aarey colony
Free Press Journal
View source
Independent source1 October 2020
Mumbai metro to suffer a loss of Rs 200 crores due to the controversial car shed shifting from Aarey Colony
Metro Rail News
View source
Independent source1 October 2019
Supreme Court Refuses To Stay Maharashtra Govt Decision To Allow Metro Car Shed At Aarey; Allows MMRCL To Seek Felling Of Trees
LiveLaw
View source

Related investigations

#16 · KB-150Under Trial

The Amrapali Group Homebuyers Fraud

Amrapali Group took money from over 40,000 homebuyers for Noida and Greater Noida flats, then diverted thousands of crores of that money into unrelated ventures while construction stalled for years. The Supreme Court eventually cancelled the group's RERA registration and handed its projects to state-run NBCC to finish.

42,000+
homebuyers left without possession of flats they had paid for, at the center of the Supreme Court's Amrapali Group case
Public Spending
#17 · KB-152Wrongdoing Confirmed

The Jaypee Infratech Insolvency and Homebuyers Case

Jaypee Infratech sold flats to over 20,000 homebuyers along the Yamuna Expressway, then defaulted on bank loans and entered insolvency in 2017. It took nearly seven years, a Supreme Court intervention, and two competing bidding rounds before the Suraksha Group finally took over the company in 2024 — with many buyers still waiting more than 15 years for possession.

22,000+
homebuyers left waiting, some for over a decade, as Jaypee Infratech's flats along the Yamuna Expressway remained unfinished through years of insolvency proceedings
Public Spending
#18 · KB-151Under Trial

The Unitech Group Homebuyers Fraud

Unitech collected over Rs 14,000 crore from nearly 30,000 homebuyers for flats it never finished, while a Supreme Court-ordered audit found its promoters had diverted thousands of crores abroad. The Chandra brothers spent years in jail, the government took over the company's board, and thousands of buyers are still waiting for their homes.

29,800
homebuyers from whom Unitech had collected roughly Rs 14,270 crore, per a Supreme Court-ordered audit, for flats not delivered on time
Public Spending